Member Solar and Wind Interconnection Checklist
Complete and submit the Wisconsin Public Service Commission Interconnection Application and Interconnection Agreement to Oakdale Electric Cooperative. These documents list the specifications of the equipment to be installed and estimates system performance. Your system provider or installer can provide this.
Contact Focus on Energy for rebate information.
Provide a copy of your liability insurance to Oakdale Electric Cooperative.
Oakdale Electric Cooperative will review your plans from your PSC application and notify you of any changes or will approve the project to proceed as planned.
Notify Oakdale Electric Cooperative when the system if ready for inspection and interconnection.
Oakdale Electric Cooperative performs a field inspection and test of the interconnected system components. Upon passing all tests and inspections, you will be cleared to begin generating energy.